Tahoe-Central Sierra Project Tracker
Project Tracker
  • About
    • ABOUT TCS PROJECT TRACKER
    • CONTACT US
  • Projects
    • Project Map
    • Full Project List
  • Program Info
    • Focus Areas
    • Pillars of Resilience
    • Performance Measures
    • Counties
    • National Forests
    • Watersheds - HUC 10
    • Watersheds - HUC 8
    • WUI Zones
    • Organizations
    • Funding Sources
    • Web Services
  • Results
    • Accomplishment Dashboard
  • Reports
    • Projects
  • Log In Toggle Dropdown
    • Forgot Password
    • Request Account
  • Help
    • Request Support
    • Training
    • Release Notes
    • About ProjectFirma
View Fact Sheet

Parcel Best Management Practices (BMP) Implementation

This Project is sourced from EIP Project Tracker
Back to all Projects
Forecasted
Planning/Design
Implementation
Post-Implementation
Completed

Contents

Project Overview

Basics

Water Security and Riparian Heath
Hydrologic Integrity
Stormwater Management
Parcel Best Management Practices (BMP) Implementation

Implementation
Project facilitates installation and maintenance of stormwater best management practices (BMPs) on developed parcels and through area-wide treatment to stabilize sediment and treat and infiltrate runoff before it enters Lake Tahoe. This project accounts for developed parcels issued BMP certificates and source control certificates for each calendar year.
Accomplishments for this project are tracked under EIP Performance Measure 4, Parcels with Stormwater BMPs. Results for this PM 4 are brought into LT Info automatically via a connection to TRPA's BMP Database and are therefore not reported directly as part of this project's accomplishments.

2007
2007
2086
1/17/2025

Project Attributes

Footprint Acres
None

Location

To zoom, hold down Shift and drag a rectangle.
Named Area: Basin-wide , Area Type: Region

None Selected


None Selected


None Selected


None Selected


None Selected

Organizations

Funders
  • California Lahontan Regional Water Quality Control Board
  • California State Water Resources Control Board
  • Commercial Property Owners
  • Douglas County, NV
  • Nevada Division of Environmental Protection
  • Nevada Tahoe Resource Team – Nevada Division of State Lands
  • Residential Property Owners
  • Tahoe Regional Planning Agency
  • U.S. Environmental Protection Agency
  • U.S. Forest Service - Lake Tahoe Basin Management Unit
  • U.S. Natural Resource Conservation Service
Lead Implementer
  • Tahoe Regional Planning Agency
Partners
  • City of South Lake Tahoe
  • El Dorado County, CA
  • Nevada Tahoe Conservation District
  • Placer County, CA
  • Tahoe Resource Conservation District
  • Washoe County, NV

Contacts

Shay Navarro (snavarro@trpa.gov)

Performance Measures

Expected Performance Measures

No expected Performance Measures set for this Project.

Reported Performance Measures

No annual Performance Measure accomplishments entered for this Project.

Financials

Budget

$350,360.00
$172,105.00
$175,360.00
$2,895.00
Total
Nevada Division of Environmental Protection (NDEP) $45,360.00 $45,360.00 $90,720.00
Stormwater Fee (TPRA) $69,701.00 $80,000.00 $149,701.00
Tahoe Regional Planning Agency (TPRA) $57,044.00 $50,000.00 $107,044.00
Total $172,105.00 $175,360.00 $347,465.00
Comment: None provided

Reported Expenditures

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Total
319 Funds (USEPA) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $181,940.00 $245,665.00 $202,634.00 $97,150.00 $121,826.00 $17,617.00 $52,927.00 $80,829.00 $9,208.00 $10,342.00 $18,817.00 $0.00 $1,038,955.00
Commercial Property Owners (Commercial) $2,450,000.00 $2,950,000.00 $3,600,000.00 $2,050,000.00 $3,500,000.00 $7,150,000.00 $2,780,000.00 $2,250,000.00 $1,580,000.00 $3,970,000.00 $910,000.00 $790,000.00 $800,000.00 $1,000,000.00 $1,550,000.00 $700,000.00 $1,550,000.00 $450,000.00 $0.00 $40,030,000.00
Douglas County General Fund (Douglas County) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $9,246.00 $5,754.00 $0.00 $0.00 $0.00 $0.00 $0.00 $15,000.00
Lake Tahoe License Plate Program (NDSL) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $5,947.00 $3,279.00 $0.00 $0.00 $0.00 $1,714.00 $7,648.00 $0.00 $0.00 $0.00 $0.00 $18,588.00
Proposition 50 (SWRCB) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $154,562.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $154,562.00
Residential Property Owners (Residential) $3,405,000.00 $7,905,000.00 $6,215,000.00 $4,618,000.00 $6,300,000.00 $2,096,000.00 $2,365,000.00 $2,020,000.00 $5,255,000.00 $2,076,000.00 $1,253,000.00 $1,506,000.00 $1,630,000.00 $1,356,000.00 $1,125,000.00 $695,000.00 $910,000.00 $810,000.00 $0.00 $51,540,000.00
Shoreline Fee (TPRA) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $8,041.00 $6,062.00 $0.00 $0.00 $0.00 $0.00 $14,103.00
Southern Nevada Public Land Management Act (NRCS) $0.00 $1,270,050.00 $410,143.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $1,680,193.00
Southern Nevada Public Land Management Act (USFS - LTBMU) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $110,539.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $110,539.00
Stormwater Fee (TPRA) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $21,290.00 $27,762.00 $47,251.00 $69,807.00 $85,409.00 $69,701.00 $0.00 $321,220.00
Tahoe Regional Planning Agency (TPRA) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $4,783.00 $79,710.00 $24,709.00 $14,223.00 $32,241.00 $53,475.00 $57,044.00 $0.00 $266,185.00
Grand Total $5,855,000.00 $12,125,050.00 $10,225,143.00 $6,668,000.00 $9,800,000.00 $9,246,000.00 $5,255,539.00 $4,606,502.00 $7,086,612.00 $6,251,913.00 $2,260,150.00 $2,422,609.00 $2,557,863.00 $2,476,907.00 $2,831,013.00 $1,506,256.00 $2,609,226.00 $1,405,562.00 $0.00 $95,189,345.00

Note: None provided

Pillars of Resilience

Pillars of Resilience

Project Details

Attachments

No attachments

No attachments

Notes

01/10/2025 3:00 PM System 2024 BMP data:
188 BMP Certificates Issued (22 of which were Source Control Certificates, SFR = 162, MFR = 17, and Commercial = 9)

In 2024 TRPA re-issued 85 BMP Certificates with a current date (6 of which were Source Control Certificates, SFR=53, MFR=22, CICU=10) after verifying BMP maintenance.

2024 private property costs estimated as $50,000 per CICU certificate issued ($450,000) and $5,000 per residential certificate issued ($810,000). Total estimated 2024 private match = $1,260,000.
01/08/2025 12:44 PM System Secured a total of $136,078.99 of NDEP NV319 funding over three years through December 31, 2027, which equals $45,359.66 annually.
02/01/2024 1:54 PM System 2023 BMP data:
213 BMP Certificates (22 of which are Source Control Certificates) with SFR = 177, MFR = 5, and Commercial = 31

In 2023 TRPA re-issued 68 BMP Certificates (5 of which were Source Control Certificates) with a current date after verifying BMP maintenance.

2023 private property costs estimated as $50,000 per CICU certificate ($1,550,000) and $5,000 per residential certificate ($910,000). Total estimated private match = $2,460,000
01/27/2023 2:41 PM System 2022 BMP data:
153 BMP Certificates (SFR= 131, MFR=8, CICU=14) Of these, 44 were SC, and 1 from an area-wide treatment program.
530 BMP Certificates (5 SC) re-issued with a current date following maintenance verification.

2022 private property costs estimated as $50,000 per CICU certificate ($700,000) and $5,000 per residential certificate ($695,000). Total estimated private match = $1,395,000
01/25/2023 5:04 PM System For 2018: accomplishments shown under Performance Measure 4 - Parcels with Stormwater BMPs: 357 BMP Certificates (50 were Source Control) with SFR= 260 (38SC), MFR = 78 (8 SC), Commercial = 19 (4 SC).

55 BMP Certificates re-issued with a current date following maintenance verification (3 SC)
02/15/2022 11:11 AM System 2021 BMP Data:
241 BMP Certificates (including 48 Source Control Certificates) with SFR = 216, MFR 9 , and Commercial = 16. Of these, TRPA issued 3 BMP Certificates to developed properties participating in an area-wide water quality treatment program. In 2021 TRPA re-issued 58 BMP Certificates with a current date after verifying BMP maintenance.

2021 cost estimates for commercial expenditures that total $1,550,000.00 includes $800,000.00 in private match from Heavenly Boulder Base Parking Lot and estimates $50,000 in match each for the remaining 15 commercial BMP certified parcels.
02/02/2021 5:13 PM System 2020 accomplishments derived from the BMP Database: 360 BMP Certificates (including 86 Source Control Certificates) with SFR= 312 (77 SC), MFR=28 (9 SC), and Commercial = 20.

Additionally, TRPA re-issued 124 BMP Certificates (including 7 Source Control Certificates) after verifying BMP maintenance and effectiveness.
01/13/2020 3:56 PM System 2019 accomplishments derived from the BMP Database directly: 342 BMP Certificates (68 were Source Control) with SFR= 294 (65 SC), MFR = 32 (2 SC), Commercial = 16 (1 SC).
Additionally, TRPA re-issued 144 BMP certificates (139 full and 5 source control) verifying BMP maintenance and effectiveness
02/08/2018 4:48 PM System For 2017: 406 BMP certificates (169 were Source Control) with SFR = 228 (36 SC), MFR = 154 (127 SC), COMMERCIAL = 24 (6 SC).
01/26/2017 3:48 PM System for 2016: 512 total (33 were source control) with SFR=337 (26 SC), MFR 103 (5 SC), COMM=81 (2 SC).
04/22/2016 3:04 PM System Annual unfunded need for the Stormwater Management Program is $215,000. 5-year unfunded need for the program is $1,075,000.
02/05/2016 4:28 PM System Consider changing "Action Priority" from Retrofitting public and private... to Installing public and private...
Consider changing "Performance Measure" from Parcels with stormwater retrofits to parcels with stormwater BMPs.
01/29/2016 10:55 AM System for 2011: 1,330 total (92 were source control) with SFR=563 (90 SC), MFR=697 (2 SC), COMM=70.
01/29/2016 10:53 AM System for 2009: 1,537 total (122 were source control) with SFR=824 (104 SC), MFR=636 (18 SC), COMM=77.
01/29/2016 10:53 AM System for 2015: 1,197 total (143 were source control) with SFR=838 (42 SC), MFR=325 (98 SC), COMM=34 (3 SC).
01/29/2016 10:50 AM System for 2008: 1,640 total (163 were source control) with SFR=828 (155 SC), MFR=753 (7 SC), COMM=59 (1 SC).
03/04/2015 8:52 AM System for 2007: 1,696 total (61 were source control) with SFR=839 (57 SC), MFR=754 (4 SC), COMM=102.
01/20/2015 10:30 AM System For 2014: 497 total (60 were source control) with SFR=358 (37 SC), MFR=94 (23 SC) and COMM 45.
10/30/2014 3:34 PM System For 2012: Total of 607 certificates (56 were source control) with SFR = 343; MFR = 121; Commercial = 143.
10/30/2014 10:13 AM System For 2013 Reporting: 579 total (63 were source control). SFR = 368 (55 source control); MFR = 153 (5 source control); Commercial = 58 (3 source control)
10/30/2014 10:11 AM System Cost assumptions for BMP implementation are derived from cost estimates developed by Northwest Hydraulics, implementation cost submitted by project implementers, and the Tahoe Resource Conservation District BMP Checklist to estimate cost of bringing property into compliance.

Single Family Residential = $5,000/implementation
Multi Family Residential = $5,000/implementation
Commercial, Industrial, Communications, Utilities = $50,000/implementation

Source Control Certifications per Implementation: SFR = $1,000; MFR = $1,000; Commercial = $10,000
10/29/2014 3:47 PM System For 2010 reporting: 823 certs for SFR, 183 MFR, 41 commercial. Added to cost of MFR into the residential property owners category for expenditures.
10/27/2014 11:28 AM System 2013 SNPLMA funding was reported by Tahoe RCD for administration/staff time for their agency.

External Links

  • Reported Performance Measures for Parcels with Stormwater BMPs
  • Stormwater Management Program
  • Tahoe Keys Landscape Conservation Guidebook

Photos

Photos

  •  

    BMP Maintenance 
(Timing: During) (~581 KB)
Credit: S Navarro

    BMP Maintenance
    (Timing: During) (~581 KB)
  •  

    BMPs at Ski Run Marina (Commercial)
(Timing: After) (~646 KB)
Credit: TRPA

    BMPs at Ski Run Marina (Commercial)
    (Timing: After) (~646 KB)
  •  

    Boulder parking barriers clustered & staggered to mimic natural conditions and set back to accommodate snow storage
(Timing: After) (~1,663 KB)
Credit: S Navarro

    Boulder parking barriers clustered & staggered to mimic natural conditions and set back to accommodate snow storage
    (Timing: After) (~1,663 KB)
  •  

    Deck Armor
(Timing: After) (~85 KB)
Credit: TRPA

    Deck Armor
    (Timing: After) (~85 KB)
  •  

    Dripline Trench
(Timing: After) (~5,431 KB)
Credit: TRPA

    Dripline Trench
    (Timing: After) (~5,431 KB)
  •  

    Driveway conveyance swale
(Timing: After) (~762 KB)
Credit: TRPA

    Driveway conveyance swale
    (Timing: After) (~762 KB)
  •  

    Driveway Infiltration System with Sediment Trap 
(Timing: After) (~1,306 KB)
Credit: S Navarro

    Driveway Infiltration System with Sediment Trap
    (Timing: After) (~1,306 KB)
  •  

    Dry Creek Bed
(Timing: After) (~123 KB)
Credit: TRPA

    Dry Creek Bed
    (Timing: After) (~123 KB)
  •  

    Fire Defensible Space 5ft Non-Combustible Perimeter
(Timing: After) (~5,801 KB)
Credit: D.Henry

    Fire Defensible Space 5ft Non-Combustible Perimeter
    (Timing: After) (~5,801 KB)
  •  

    Gravel Infiltration below Deck
(Timing: After) (~2,078 KB)
Credit: TRPA

    Gravel Infiltration below Deck
    (Timing: After) (~2,078 KB)
  •  

    Installation of Driveway BMPs
(Timing: During) (~156 KB)
Credit: TRPA

    Installation of Driveway BMPs
    (Timing: During) (~156 KB)
  •  

    Linear Rock Lined Infiltration Basin
(Timing: After) (~113 KB)
Credit: TRPA

    Linear Rock Lined Infiltration Basin
    (Timing: After) (~113 KB)
  •  

    Rock armor
(Timing: After) (~3,737 KB)
Credit: TRPA

    Rock armor
    (Timing: After) (~3,737 KB)
  •  

    Sediment Trap to Rock Lined Basin
(Timing: After) (~588 KB)
Credit: Douglas

    Sediment Trap to Rock Lined Basin
    (Timing: After) (~588 KB)
  •  

    Slotted channel drain conveyance to sediment trap to infiltration system
(Timing: After) (~96 KB)
Credit: NTCD

    Slotted channel drain conveyance to sediment trap to infiltration system
    (Timing: After) (~96 KB)
  •  

    Storm Chamber Subsurface Infiltration System
(Timing: During) (~185 KB)
Credit: TRPA

    Storm Chamber Subsurface Infiltration System
    (Timing: During) (~185 KB)
  •  

    Vegetation and Mulch
(Timing: After) (~1,007 KB)
Credit: S Navarro

    Vegetation and Mulch
    (Timing: After) (~1,007 KB)

Credits: The Tahoe Central Sierra Project Tracker tool has been developed through generous funding from the California Tahoe Conservancy. This project tracker was created and developed by TCSI and Environmental Science Associates.

ProjectFirma is a service provided by Environmental Science Associates (ESA), which builds on the Tahoe Regional Planning Agency's EIP Project Tracker. This program is free software; you can redistribute it and/or modify it under the terms of the GNU Affero General Public License as published by the Free Software Foundation. Source code is available on GitHub.

Copyright (C) 2025 Tahoe Regional Planning Agency and ESA | Code last updated (compiled) at 2025-07-08 21:24:44.