Hazardous Fuel Reduction Surrounding Water Delivery Infrastructure
This Project is sourced from EIP Project Tracker
Project Overview
Basics
Hazardous Fuel Reduction Surrounding Water Delivery Infrastructure
Planning/Design
The Tahoe Water for Fire Suppression partnership consists of 17 water service agencies within the Tahoe Basin. This partnership works together to promote fire protection. This project is a basin-wide programmatic approach to protecting water infrastructure by providing fuels reduction activities at each of the partner agencies' water delivery infrastructure sites. Upon completion of the Vegetation Management Plan, this project consists of fuels reduction work at the recommended water service agency sites throughout the Basin.
2021
2025
2025
1/28/2025
Project Attributes
Footprint Acres
None
Location
Named Area: Basin-wide
, Area Type: Region
None Selected
None Selected
None Selected
None Selected
None Selected
Organizations
Contacts
Donielle Morse
(dmorse@stpud.us)
Performance Measures
Expected Performance Measures
Acres of Forest Fuels Reduction Treatment | Critical Zone: Unspecified Treatment Phases: Unspecified Treatment Type: Unspecified | Not Provided |
Reported Performance Measures
Reported Performance Measures are not relevant for Projects in the Planning/Design stage.
Financials
Budget
Comment: | None provided |
---|
Reported Expenditures
2021 | 2022 | 2023 | 2024 | 2025 | Total | |
---|---|---|---|---|---|---|
U.S. Forest Service (USFS - LTBMU) | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
Grand Total | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
Note: | None provided |
---|
Pillars of Resilience
Pillars of Resilience
No Pillars of Resilience set for this Project.
Project Details
Attachments
No attachments
No attachments
Notes
01/17/2025 2:57 PM | System | 2024 Update: Fuels reduction planning is complete, and implementation work will begin in spring 2025. |
||
01/25/2024 12:31 PM | System | 2023 Update: Implementation of the fuels reduction work is dependent upon the completion of the Fuels Treatment at Critical Infrastructure Sites project (Vegetation Management Plan) 02.01.01.0127 - Fuels Treatment at Critical Infrastructure Sites. Once that project is complete, fuels reduction work on identified land will begin and continue through summer 2025. |
||
01/17/2023 9:21 AM | System | The next phase of this project is to complete a Vegetation Management Plan (VMP) for the priority infrastructure treatment sites identified in the 2021 FVA on the California side. A Registered Professional Forester will be contracted to develop a VMP that will include treatment plans for each high-priority site. STPUD, TCPUD, NTPUD, and Lukins Brothers Water Company will use the VMP for fuel reduction/defensible space planning and implementation. |
External Links
No External Links entered.
Photos
Photos
No Photos available.